Switchboard
This page provides information as to label requirements fror the for the home switchboard system.
Category
Switchboard
Location
Side of house
This page provides information as to label requirements fror the for the home switchboard system.
Switchboard
Side of house
The Standard required will depend on the type of design and/or installation.
| Standard | Title | Version Referenced |
| AS/NZS 3000 | Electrical Installations (known as the Wiring Rules) | 2018 Amendment 1&2 |
| AS/NZS 4777.1 | Grid connection of energy systems via inverters | 2024 |
| AS/NZS 5033 | Installation and safety requirements for photovoltaic (PV) arrays | 2021 |
| AS/NZS 5139 | Electrical installations – Safety of battery systems for use with power conversion equipment | 2019 |
SKU 0032
AS/NZS 5033:2021
Clause 5.4
PV DP Green Reflective Fire Sign
Where a disconnection point is used as the isolation method.
SKU 0033
AS/NZS 5033:2021
Clause 5.4
PV SW Green Reflective Fire Sign
Where a load break disconnection device is used as the isolation method
SKU 0034
AS/NZS 5033:2021
Clause 5.4
PV AC Green Reflective Fire Sign
For Inverters where the calculated PV d.c. circuit maximum voltage is less than 120V d.c. at the inverter PV input, and the PV modules are within 1.5m of the inverter are installed ie, Micro inverter systems
SKU 0741
AS/NZ5033:2021 Clause 5.7
&
AS/NZ4777.1 2024 Clause 6.2
Shutdown Procedure
Placed adjacent to and visible from the equipment to be operated. i.e. “INVERTER”.
Where the inverter is adjacent to the switchboard it is directly connected to, the shutdown procedure may be placed in the switchboard.
Where the building has a fire panel, an additional sign shall be placed at the fire panel with instructions as to the location of the IES Emergency shutdown procedure (Refer label below).
SKU 0159
AS/NZ5033:2021 Clause 5.7
&
AS/NZ4777.1 2024 Clause 6.2
Warning PV Array DC Isolators Do not De-Energize the PV array
Located under the Shutdown procedure. Where the energy source is not de-energised when the IES is shutdown. A warning shall be included in the emergency shutdown indicating that isolation of the energy source, by shutting down the inverter and isolating the IES , may not de-energise the energy source and further action may be required.
SKU 0596
AS/NZ4777.1 2024
Clause 6.3(g)
Warning Multiple Supplies Isolate all Supplies before working on this “Switchboard”
Located at the Switchboard in a prominent position on the switchboard and visible to personnel operating the switchboard.
SKU 0721
AS/NZ4777.1 2024
Clause 6.3(b)
Main Switch Grid
Where the inverter is connected to the main switchboard, the main switch for the grid supply shall be labelled Main Switch (GRID)
SKU 0722
AS/NZ4777.1 2024
Clause 6.3(a)
Main Switch (INVERTER)
AS4777.1 2024 6.3 (a) The Main Switch for the IES Supplementary supplies shall be labelled Main Switch (INVERTER)
SKU 0723
AS/NZ4777.1 2024
Clause 6.3(a)
Main Switch Solar (INVERTER)
Where there is more than one IES supplementary supply other wording associated with the energy source may be added to the label eg.
SKU 0723
AS/NZ4777.1 2024
Clause 6.5
Inverter Location
Placed on the Switchboard where the inverter is not within 3 meters and fully visible from the main switchboard / and or fire panel
SKU 0019
AS/NZ5033:2021
Clause 5.6.1.1
&
AS/NZ4777.1 2024
Clause 6.5
Solar Array on Roof V A
Located in switchboard
This label Is not specified in the latest standard, however still used by many,
Now a requirement if included with Solar System Layout. “Site map”
SKU 0022
AS/NZ5033:2021
Clause 5.3.2
Warning Hazardous DC Voltage
Located on any Array junction box containing PV DC Cable terminations.
Does not apply to PV array disconnecting devices as they have their own labelling requirements
SKU 0035
Energy Safe Victoria
Institute of Electrical Inspectors.
Warning This Premise Contains an Electricity Generation System
Located at the Fire indicator panel, Main switchboard and all Switchboards where an IES is directly connected.